Work Day 19th November 2016

Not a lot of detail to report this week as it was a day progressing with removing more paint from the LCP roof. To make the roof access easier we borrowed a gantry, a bit big (understatement) but it allowed us access at roof level.

Access Gantry 2 wm.jpg

One more working session should see the paint removal completed. Next job will be to replace all the corroded aluminium pop rivets on the LCP roof of which there are many.

LCP Roof 1 wm.jpg

LCP Roof 2 wm.jpg